How to Check Contractor Bills and Avoid Overbilling in House Construction
Most budget overruns in house construction don't come from one big mistake. They come from many small billing differences across running bills. Here is a practical checklist to verify each bill before you pay.
1. Check the quantity, not just the total
Every bill should list items with quantities and rates. Compare each quantity with the drawings and your BOQ. If the bill says 120 sqm of plastering for a floor whose BOQ quantity is 95 sqm, ask how it was measured.
2. Make sure deductions for openings are made
Masonry, plastering and painting quantities should have deductions for doors, windows and other openings as per the agreed method of measurement. Missing deductions are one of the most common reasons bills run high.
3. Watch for items billed twice
The same work can appear under two descriptions, for example plastering included in a masonry rate and billed again separately, or shuttering billed separately when the RCC rate already includes it. Read the BOQ item description to see what each rate includes.
4. Control extra items
Work not in the BOQ should be agreed in writing, with quantity and rate, before it is done. Extra items that appear only on the final bill are hard to verify and easy to dispute.
5. Check rates against the agreement
Rates on each bill should match the agreed BOQ rates. If a rate change is claimed for material price movement, it should follow what was agreed in the contract.
6. Track cumulative quantities
Each running bill should show the previous total, this bill and the cumulative total. If cumulative quantities exceed the BOQ quantity for an item, that needs an explanation.
7. Measure on site for the big items
For high-value items like concrete, steel and flooring, a joint measurement on site with your engineer or consultant is worth the time.
Get an independent check
If you don't have the time or technical background to verify bills, an independent quality and quantity audit compares billed quantities with drawings and site measurements and flags the differences, often saving far more than it costs.
Frequently asked questions
How do I know if my contractor is overbilling?
Compare each item's billed quantity with the drawings and BOQ, check deductions for openings, look for items billed twice, and confirm rates match the agreement.
What is a running bill?
An interim bill raised during construction for work completed so far. It should show previous, current and cumulative quantities for each item.
Should extra work be approved in writing?
Yes. Agree the quantity and rate for any work outside the BOQ before it is done. It is the simplest way to avoid disputes at the final bill.